Generators File Complaint to Disqualify Demand Response From ISO-NE Capacity Auction

November 17,2014



The New England Power Generators Association has filed a complaint at FERC to disqualify Demand Response Capacity Resources from participating as supply in the Forward Capacity Auction (FCA) for the 2018/2019 Capacity Commitment Period and to exclude such resources from participating as supply in the Forward Capacity Market (FCM) going forward

NEPGA cited an appeals court ruling which previously held that FERC lacks jurisdiction over demand response as requiring its sought relief.

NEPGA said that, "The effect on clearing prices of including Demand Response Capacity Resources in FCA 9 and subsequent FCM auctions cannot be estimated with any degree of precision, but NEPGA would expect it to be substantial given the amount of Real-Time Demand Response that cleared in past FCAs."

See NEPGA's complaint for more



Tags:
FERC   Demand Response   ISO New England   New England  

Comment on this story


ADVERTISEMENT
NEW Jobs on RetailEnergyJobs.com
TPV-SALES-EXECUTIVE -- Back Office Provider -- Other
Sr-Market-Risk-Analyst -- Wholesale Supplier/Trader -- New York - New York City Metro
Energy-Regulatory-Specialist -- Other -- Other
More Stories on RetailEnergyX.com:
FERC Orders $230 Million In Penalties Against GreenHat, Related Parties '
FERC Issues Show Cause Order To GreenHat With Proposed $229 Million Fine For Alleged 'Manipulation'
FERC Rules That Entering Bilateral FTR Data Into PJM System Does Not Create A Separate Contract
Danly Named FERC Chairman
FERC States Intent To Revoke MBR Authority Of Several Retail Suppliers


comments powered by Disqus





Advertise here:
Email retailenergyx@gmail.com


Events Jobs Contact Migration Stats Supplier Lists Municipal Aggregation

About Disclaimer Privacy Terms of Service

Home


Developed by: Avidweb Technologies inc.