PJM Announces New Capacity Performance Transitional Auction Timeline

July 24,2015



In light of FERC's directive to allow non-generation resources to participate in the PJM capacity performance transitional auctions, PJM announced PJM will adjust the schedule for two of its upcoming transitional capacity auctions to allow demand response and energy efficiency providers to participate.

The July 22 decision by FERC instructs PJM to allow demand response and energy efficiency providers to bid into transition auctions originally planned for July 27 and Aug. 3. Exact dates for the rescheduled transition auctions will be announced soon, "but they will likely be in the weeks following the base residual auction," PJM said

PJM’s Base Residual Auction for the 2018/2019 delivery year is unaffected and will be held Aug. 10.

Tags:
PJM   Capacity Auction   Capacity Performance   FERC   Capacity Market  

Comment on this story


ADVERTISEMENT
NEW Jobs on RetailEnergyJobs.com
TPV-SALES-EXECUTIVE -- Back Office Provider -- Other
Sr-Market-Risk-Analyst -- Wholesale Supplier/Trader -- New York - New York City Metro
Head-of-Retail-Operations -- Wholesale Supplier/Trader -- Other
Energy-Regulatory-Specialist -- Other -- Other
More Stories on RetailEnergyX.com:
FERC Orders $230 Million In Penalties Against GreenHat, Related Parties '
FERC Issues Show Cause Order To GreenHat With Proposed $229 Million Fine For Alleged 'Manipulation'
SPP, MISO Institute Rotating Outages, Showing ERCOT 'Energy-Only' Market Design Not Cause Of Outages
FERC Rules That Entering Bilateral FTR Data Into PJM System Does Not Create A Separate Contract
Danly Named FERC Chairman


comments powered by Disqus





Advertise here:
Email retailenergyx@gmail.com


Events Jobs Contact Migration Stats Supplier Lists Municipal Aggregation

About Disclaimer Privacy Terms of Service

Home


Developed by: Avidweb Technologies inc.