ERCOT Posts Draft Coordination Plans With SPP, MISO
January 15,2019
ERCOT said in a market notice that, in order to update and clarify operating procedures concerning shared assets, including Switchable Generation Resources (SWGRs), Block Load Transfers (BLTs), and Direct Current Ties (DC Ties), ERCOT, SPP, and MISO conducted a thorough review of the existing coordination documents entered into by ERCOT and SPP in 2014, and ERCOT and MISO in 2013.
The primary objective of the review was to ensure reliability-based actions involving shared assets are facilitated as reliably and expeditiously as possible in the event of Emergency Conditions.
As a result of the review, ERCOT and SPP prepared a draft ERCOT-SPP Coordination Plan, and ERCOT and MISO prepared a draft ERCOT-MISO Coordination Plan.
The coordination plans do not create any legal obligations, but instead establish mutually agreeable operational procedures with respect to shared assets.
In connection with Nodal Protocol Revision Request (NPRR) 886, Agreements between ERCOT and other Control Area Operators, ERCOT committed to notify its Market Participants, to the extent possible, prior to entering any agreement with another Control Area Operator concerning coordination of SWGRs, DC Ties, or BLTs. While NPRR 886 has yet to be approved, ERCOT provides this Notice to Market Participants in order to allow them time to review and comment on the ERCOT-SPP Coordination Plan and ERCOT-MISO Coordination Plan prior to their execution. ERCOT will consider all comments submitted by January 28, 2019 and discuss its acceptance or rejection of those comments with the Technical Advisory Committee (TAC) on January 30, 2019 and the ERCOT Board on February 12, 2019 prior to execution of the plans.